Kerbing Scheme Completion – work to restart on Thursday Feb 11th

Work to complete the Wroxton Lane kerbing scheme is expected to take up to 3 days starting from Thursday February 11th

road closed

This will involve the contractor laying the correct colour conservation kerbs.

Once again, during this time the road will be closed to through traffic but with access to frontages and for emergency vehicles, and no parking along the section affected.

The contractor has apologised for the inconvenience caused by his mistake and thanks you for your patience. The end is in sight!

Kerbing Scheme Delay

Completion of Kerbing Scheme in Wroxton Lane Delayed

road sign

Unfortunately the County Council’s contractor has ordered the wrong kerbs, and has installed them.  The Parish Council had asked for conservation kerbs in a colour known as harvest buff, which is the best match for the existing street scene, but the kerbs which have laid are a much lighter colour.  Consequently the contractor has been asked to remove the kerbs laid and replace them with the correct colour at their own cost.

It is regrettable that there will be a delay to  completion, but the road will remain open to traffic in the interim.  The Parish Council sincerely regrets the inconvenience, but is determined to see the job completed using the materials originally selected. They will keep you updated as to an expected finish date.